Roof and Painting Schedule

Below is a schedule of when buildings have been painted and roofed. It is incomplete, if you live in one of the building with a ? mark and can fill in the date please send the information to scrollbiz@comcast.net and we will update the information.

Bright Passage

Roofed

Painted

Building 1a-e11(2-10) original 2009
Building 2 a-e11(12-20) ? 2009
Building 3 a-e11 (22-30) ? ?
Building 4 a-e11 (32-40) ? 2009
Building 5 a-e11 (42-50) ? 2005
Building 6 a-e11 (52-60) original 2005
Building 7 a-e11 (62-70) 2006 2006
Building 8 a-e11 (72-80) original 2005

Lakeview Court

Building 1 a-e (2-10) 2003 2005
Building 2 a-e (1-9) 2003 2004
Building 3 a-e (11-19) 2003 ?
Building 4 a-e (21-29) 2009 2006
Building 5 a-e (31-39) 2003 2004

Liftside Drive

Building 6 a-e (1-9) 2003 2006
Building 7 a-e (11-19) 2005 2002 or 2003
Building 8 a-e (21-29) 2004 ?

Slopeside Terrace

Building 9 a-e (21-29) 2004 2004
Building 10 a-e (11-19) 2004 2006
Building 11 a-e (1-9) 2004 2003 or 2004

Winding Way

Building 12 a-e (1-9) 2003 2006
Building 13 a-e (11-19) 2004 2003
Building 14 a-e (21-29) 2004 ?
Building 15a-e (31-39) 2004 ?
Building 16 a-e (32-40) 2006 back 1994
Building 17 a-e) (22-30) 2004 2004
Building 18 a-e (12-20) 2005 2006
Building 19 a-e (2-10) 2011 ?